Topics in this domain

Project Roles and Governance

Project management · 3 min read

Everyone has a job

An IT project is like building a house. Someone pays and decides what they want (the sponsor). A site manager runs the work (the project manager). The future residents say what they need and check the result (the users). An inspector checks it’s built properly (quality assurance). When these roles blur, projects drift, overspend or deliver the wrong thing.

Project roles: sponsor, steering committee, project manager, user management, quality assurance, IS auditor.
RoleResponsibility
Senior managementCommits resources and approves the project as part of the portfolio
Project sponsorSenior business executive who owns the business case, provides funding, champions the project, and is accountable for benefits
Steering committeeOverall direction; reviews progress at stage gates; approves major changes to scope, budget or schedule; resolves escalated issues; decides go or no-go
Project managerPlans, organises, staffs and controls the project day to day, within the agreed scope, time and budget
User managementDefines requirements, provides subject experts, takes part in testing, and formally accepts the system
Development managementProvides the technical people and delivers the solution
Quality assuranceIndependently reviews deliverables and checks standards and methods are followed
Security officerMakes sure security requirements are defined and met
IS auditorAdvises on controls and reviews project risk and governance, without making management decisions

Three ways to organise a project

Functional, matrix and projectised structures, from least to most project manager authority.
StructureProject manager’s authorityMain issue
FunctionalLow; the department head decidesThe project competes with normal work
Projectised (dedicated team)HighCostly; the team breaks up at the end
MatrixShared with department managersStaff have two bosses and clashing priorities

Keeping a project under control

  • An approved business case before significant spending
  • Stage gates where the steering committee checks the project is still worth doing and ready for the next stage
  • Change control over scope, budget and schedule, with set approval levels
  • Honest status reporting on progress, risks and issues
  • Quality and risk management throughout
  • Closure: formal acceptance, handover and lessons learned

The auditor on a project

The IS auditor can be involved throughout a project, checking that controls are designed in, that governance works, and that risks are managed. The auditor:

  • reviews business cases, requirements and designs for controls and audit trails
  • attends steering committee meetings as an observer or adviser
  • reviews test plans and results
  • assesses readiness before go-live

The auditor doesn’t approve deliverables, design controls or make go/no-go decisions. That would impair their independence when auditing the system later.

Example. A CRM project’s steering committee approves a 40% scope increase proposed by the vendor, without the sponsor present and without updating the business case. The auditor reports a governance weakness: major changes should be assessed against the business case and approved by the sponsor.

How the exam asks about it

If the question asks…The answer is usually…
Who is accountable for project benefits?The project sponsor
Who approves major scope changes?The steering committee (with the sponsor)
Who accepts the system?User management
The auditor’s role in a projectAdvice and independent review; no decision-making
Main risk of a matrix structureConflicting priorities between project and department managers

In short

  • The project sponsor owns the business case and funding, and is accountable for the project delivering its benefits.
  • The steering committee gives direction and makes the big decisions: scope, budget, and go or no-go at stage gates.
  • The project manager plans and runs day-to-day delivery within the agreed limits.
  • User management defines requirements, takes part in testing, and formally accepts the system.
  • Quality assurance independently reviews deliverables and process.
  • The IS auditor advises on controls and reviews risk, without making management decisions.
  • Projects can be organised functionally, as a dedicated team (projectised), or as a matrix; matrix splits authority and causes priority clashes.

Exam traps

  • The sponsor, not the project manager, is accountable for business benefits.
  • The steering committee decides on major changes; the project manager proposes them.
  • Acceptance is the users' decision, not IT's.
  • An auditor who signs off a project deliverable loses independence.
  • In a matrix structure, conflicting priorities between department and project managers are the main risk.

Slides

Click the slide and use the arrow keys. F toggles full screen.

CISA · Domain 3 · Project management

Project Roles and Governance

Who does what on an IT project, how a project is kept under control from start to finish, the three ways to organise a project team, and the auditor's place in it.

1 / 9